Anatomy of a Delay Claim
There are three crucial components of a successful
delay claim:
 | Legal entitlement |
 | Causation |
 | Quantification |
A contractor must be able to prove legal entitlement
to the claim. In most cases, this involves reviewing the
contract, establishing a breach and demonstrating that
the contractor complied with important provisions of the
contract.
The causation component normally involves an accurate
analysis of the critical path method (CPM) schedule to
prove that the breaches in the contract caused the
delay. There are many methods for preparing a schedule
analysis including total time, impacted as planned,
impacted as built, and contemporaneous time-frame
analysis. Some of these methods which were acceptable
ten years ago, are now often rejected by arbitrators and
judges.
The quantification of the delay damages should result
in a fair and reasonable claim that is supported by the
job cost and accounting records. In determining the best
method (total cost, modified total cost, discrete, or
other) for calculating the damages, a contractor should
carefully consider facts of the case, as each method has
advantages and disadvantages. Then, a thorough review of
the contract, state and federal law and case precedence
should be conducted to determine the allowable cost
components to be included in the claim. Usually, a
contractor submits a claim for direct "brick and
mortar" costs (including lost productivity,
acceleration, escalation, additional work, etc.),
extended general conditions (job site overhead), and
unabsorbed home office overhead (extended general and
administrative expenses, usually recovered using the
Eichleay formula).
A Case Study: The New Jamestown Bridge

The New Jamestown Bridge project in Rhode Island
experienced substantial design, administrative and
construction problems resulting in a complicated $55
million claim. Through an in-depth investigative process
that studied the fine details of the claim while still
maintaining the large perspective Mr. Lee was able to
significantly challenge the contractor's claim thus
leading to a mediated settlement for about 1/3 of the
claim.
The bridge had been partially completed under two
previous contracts. The third contractor completed four
months late and submitted a detailed claim prepared by a
"Big 5" accounting expert with support from a
nationally recognized lost productivity expert and CPM
scheduling expert. $1.2 million was paid to these three
experts to prepare the claim.
$14 million of the claim was for additional labor and
equipment costs for lost productivity due to overtime
and damages due to interference. This was 50% of the
direct cost portion of the claim.
The underlying argument for the lost productivity due
to overtime was that design problems, late approval of
submittals and change order requests, and rejection of
time extension requests forced the contractor to
accelerate. The lost productivity expert relied on the
statistics in The Business Roundtable report,
"Scheduled Overtime Effect on Construction
Projects," to determine the percentage lost on a
weekly basis for labor and equipment costs. The expert
had used the total labor hours on the project as the
basis for calculating the claim instead of determining
the actual labor hours for each phase of work.
Anthony Lee's Role
When Mr. Lee was retained to investigate this claim,
he began by reviewing the detailed payroll records and
time cards. He found there was excessive overtime only
in driving the piles for the trestle, while the other phases -- including
pier footings, pier shafts, pier caps and spans,
incurred sporadic, and unscheduled overtime -- were not
extensive enough to meet the lost productivity standards
in The Business Roundtable report. Additionally,
the heavy overtime in pile driving had been planned per
a review of the details in the bid take-off sheets, and
had therefore not been incurred by the owner's
interference. Mr. Lee was able to show that there was no
unplanned extended scheduled overtime resulting in lost
productivity.
The "Big 5" accounting expert
calculated
the damages caused by interference using the measured
mile method. This is a widely accepted method where the
contractor compares the performance during a non-impacted period to the impacted performance period,
and calculates the difference as damages. However, the
legal argument claimed interference and interruption
continually throughout the project and, therefore, there
was no non-impacted period against which to measure
performance. In actuality, the accounting expert used
the "lowest cost" period as the base.
When Mr. Lee reviewed the detail of costs and the
procedures for allocating them to different periods, he
found that the contractor increased equipment charges by
$9 million when converting equipment costs to bluebook.
Most of the increase ended up in the claim. This was a
Trojan Horse claim. The contractor rode the claim in on
charges of damages caused by interference but, when the
details inside the claim were revealed, the so-called
damages were caused more by a questionable conversion of
actual equipment costs to blue-book values.
The CPM scheduling expert concluded that the
contractor accelerated the project by over two years so
that it was "only" four months late. The scheduling expert concluded that the contractor was very
efficient in working overtime hours and accelerated the
completion date by over two years, while the lost
productivity expert concluded that the contractor was
very inefficient in working overtime hours. This was a
"big picture" contradiction.
A preparer, or defender, of a complicated
construction claim has to continually keep "the big
picture" and "the smallest details"
in focus. Every claim is different, and a claims consultant has to bring all of his knowledge and
experience to bear in the review of each claim. |